In this section, we gather all relevant dates and deadlines concerning new versions of APIs, deprecating old versions, testing phases, etc. Also, the roadmap and timelines announced by DG EAC, which have an effect on the technical community, are highlighted.

Schedules and timelines are also shared with the technical community at the Infrastructure Forum meetings and via the EWP providers mailing list.


 Timeline for IIA release 7.0.0

Phase

Task description

Target date

Jul 2023

(tick) Draft of versions 6.3.0 and 7.0.0 presented to the technical community at the Infrastructure Forum meeting

21/07/2023

Jul 2023

(tick) Time for review and preparation of the final version

End of Jul 2023

Aug 2023

(tick) Official release of versions 6.3.0 and 7.0.0

01/08/2023

Sep 2023

(tick) Discussions to clarify and support correct implementation of specifications in Github and during Infrastructure Forum meeting.

20/09/2023

Oct 2023

(tick) Technical workshop in Warsaw for all types of providers. Discussions to clarify and support implementation of the 6.3.0 and 7.0.0 releases. Testing of 6.3.0 in DEV - those installations which are ready.

Oct 3-4, 2023

Oct 2023

(tick) Discussions to clarify and support correct implementation of specifications in Github and in Infrastructure Forum meetings.

18/10/2023, 15/11/2023, 13/12/2023

By end 2023

(tick) Implementation of validators for IIAs 7.0.0 (done 30/11/2023).

End of 2023

Feb 2024

(tick) On-site and/or remote technical workshop for providers to test IIA version 7.0.0.

Feb 2024

Mar 2024

Provided implementations are ready, nodes switch to version 7.0.0. During that week, users should not plan any exchanges of IIAs in PROD. Versions older than 7.0.0 will be defined as DEPRECATED.

Mar 25-31, 2024

 Testing Sessions for IIA Release 7.0.0
testing-sessions-schedule-february-2024.png

 Timeline for deployment of the enhanced version of the Registration Portal

Phase

Task description

Target date

Sep 2023

(tick) Providers register and upload data to the DEV installation of the enhanced Registration Portal (RP).

30/09/2023

02/10/2023

(tick) Official launch of the enhanced RP in the DEV network. DEV Registry switches from the old source file to the new source file.

Action buttons are deactivated in the old RP in DEV.

02/10/2023

Oct 2023

(tick) Tuning the enhanced RP, gathering comments from providers.

30/10/2023

30/10/2023

(tick) Removing installation of the old RP in DEV.

30/10/2023

Nov 2023

(tick) Providers register and upload data to the PROD installation of the enhanced RP.

05/11/2023

09/11/2023

(tick) Official launch of the enhanced RP in the PROD network.

Action buttons are deactivated in the old RP in PROD.

09/11/2023

30/11/2023

(tick) Removing installation of the old RP in PROD.

30/11/2023